MODELL’S SPORTING GOODS
- Monitored escalator fabrication with China
- Liason between mall, tenant, and municipality
- Coordinated with fire marshall on fire alarm design
- Handled structural engineering at escalator opening
- Complete new M/E/P/S systems
- Fast track escalator installation
This project included stripping the entire multi-level space and building-out a new interior. Project was completed for the holiday season and required a dual store scheduling approach. A key project issue involved the installation of two escalators and a new ADA elevator.